The Building Safety Regulator (BSR) has published its latest building control data for higher-risk buildings (HRBs) in England, covering the 12 weeks to 1 November 2026. Across all categories, 92% of gateway 2 decisions were approvals: 370 of 403 decisions, covering 19,409 homes.
For new HRBs and conversions, the approval rate was 95%, and the median approval time fell to 20 weeks. In London, where around 60% of new-build applications in progress sit, the approval rate was 97%, and 29 of the 40 new-build decisions in the period were London schemes.
The headline numbers
| Application type (national) | Approval rate | Median approval time |
|---|---|---|
| New HRBs and conversions | 95% | 20 weeks |
| External remediation | 93% | 32 weeks |
| HRB internal works | 91% | 30 weeks |
| NHS internal works | 86% | 20 weeks |
Some points from the commentary matter for programmes:
- The statutory clock is still not the real one. The law gives the regulator 12 weeks to decide a valid application for a new HRB and 8 weeks for work to an existing one, unless an extension is agreed. Medians of 20 to 32 weeks are well above that, and complex new-build cases are tracked separately, at a median of 35 weeks.
- A levy-driven surge is being triaged. New-build applications jumped to 64 in September, ahead of the Building Safety Levy coming into force on 1 October 2026, then dropped to 6 in October. Of the 41 late-surge applications, 18 were judged poor quality and paused, and 8 were recommended for rejection, subject to final review.
- Internal works dominate the workload. There are 1,116 HRB internal works applications in progress nationally, 751 of them in London, and the BSR says it is adding capacity for this category.
- Major changes take time too. There were 242 live major change requests. New-build requests closed in a median of 7 weeks, against a statutory 6.
- Gateway 3 is coming into view. No new-build project approved at gateway 2 has reached gateway 3 yet. The BSR says inspections have already found a small amount of work that deviates from the designs agreed at gateway 2.
What it means for London projects
For building services, the message is that a complete, well-coordinated application is what moves quickly. The BSR says better-quality remediation applications can now be decided in around 15 weeks, while poor submissions are paused or rejected. MEP information is a large part of that quality: fire strategy interfaces, smoke control, sprinkler and wet riser design, fire-stopping at service penetrations, and the plant spaces and routes that support them.
In practice, that means:
- Fix the MEP design earlier. Gateway 2 needs design that shows compliance, not design intent. Working with MEP consultants in London who design to that level before submission avoids late redesign.
- Coordinate before you submit. Riser layouts, ceiling voids and penetrations through compartment walls should be resolved in the model. Structured BIM coordination and clash detection in BIM make the submitted drawings consistent with each other.
- Plan for change control. Every change to fire-related services after approval can become a notifiable or major change. Lock down equipment selections and routes early, and keep a clear record of what was approved.
- Build what was approved. With the BSR already flagging deviations on site, installers need the approved information on site, and the installation has to match it.
For residential and mixed-use blocks across the capital, an experienced team of MEP contractors in London that carries the design through to installation and commissioning reduces the risk of a mismatch at gateway 3. Our building services engineers in London can review where a scheme stands before it is submitted.