Clash detection in BIM: a practical guide for MEP coordination

How clash detection in BIM works on MEP projects: federated models, Navisworks clash tests, tolerances, the clash matrix and coordination meetings.

Monitor showing a 3D BIM model of ductwork, pipework and cable trays with two clashes highlighted in red

Clash detection is one of the main reasons for building an MEP model in 3D. Ductwork, pipework, cable containment and sprinklers all compete for the same ceiling void, and the void is always smaller than the architect hoped. Finding a duct running through a beam on screen costs minutes. Finding it on site costs days, materials and goodwill.

Yet many projects run clash detection and still end up with clashes on site. Running the software is the easy part. What matters is how the tests are set up and how the results are resolved. This guide explains how clash detection in BIM works on real MEP projects and what makes it effective.

What clash detection is

Clash detection is the automated comparison of 3D models to find places where elements overlap or come too close. On a building services project that usually means comparing:

  • the MEP models (mechanical, electrical, public health, sprinklers) with each other;
  • the MEP models with the structural model (beams, columns, slabs, bracing);
  • the MEP models with the architectural model (ceilings, walls, risers, doors).

The models are usually authored in Revit MEP and combined in a federated model. Clash detection in Navisworks is the most common way to test them, although other coordination platforms do the same job.

Hard, clearance and workflow clashes

Not every clash is a physical collision:

  • Hard clashes: two elements occupy the same space. A duct passes through a beam, or a pipe through a cable tray.
  • Clearance (soft) clashes: elements do not touch but break a required clearance. Examples are insulation thickness, access to a valve, maintenance space in front of a fan coil, or the zone needed to lift a ceiling tile.
  • Workflow or 4D clashes: elements that fit in the finished model but cannot be installed in that sequence. A large duct may need to go in before a pipe that passes underneath it.

Clearance clashes are the ones most often skipped, and the ones that cause the most trouble at handover. A model that fits but cannot be maintained has not been coordinated.

Model quality comes first

Clash detection is only as good as the models being tested. Before running tests, check that:

  • Every model uses the same coordinates and levels. A shared origin and survey point avoid thousands of false clashes.
  • Insulation and hangers are modelled where they matter. A pipe modelled without its insulation can pass the test and still clash on site.
  • The level of detail suits the stage. Testing a concept model at fabrication-level tolerance creates noise. Our note on LOD 300 vs LOD 400 explains what each level should contain.
  • The models are current. Federate the latest issued versions, not files saved locally last week.

Setting up the tests

A good clash test is narrow and deliberate. Rather than testing everything against everything, set up a clash matrix: a grid showing which discipline is tested against which, at what tolerance and in what priority order. A typical order is:

  1. Structure against all MEP, because structure rarely moves.
  2. Large ductwork against everything else, because ducts are the hardest services to reroute.
  3. Gravity drainage against other services, because falls cannot be compromised.
  4. Pressurised pipework against cable containment.
  5. Sprinklers against everything, with clearance rules for heads.
  6. Clearance tests for access zones, ceiling grids and maintenance space.

Tolerances matter. Too tight, and the report fills with trivial touches. Too loose, and real problems slip through. Set tolerances per test, and group results by area, level or system so that one rerouted duct does not appear as fifty separate clashes.

Resolving clashes: the coordination cycle

Software finds clashes; people resolve them. Effective BIM coordination runs as a regular cycle, often weekly during design:

  1. Run the tests on the latest federated model.
  2. Review and group the results, discarding false positives and combining related clashes.
  3. Assign each group to a responsible discipline with a clear action, such as “lower duct by 150 mm” or “move tray to the east side of the corridor”.
  4. Agree in a coordination meeting with the screen shared, so everyone sees the same view.
  5. Update the models and rerun the tests to confirm the clash is resolved and no new ones have appeared.

The rules for who moves are agreed at the start of the project: gravity drainage keeps its route, large ducts take priority over small pipes, and so on. That prevents the same argument at every meeting.

Reports that people actually use

A good clash report is short and visual. Include a screenshot of each grouped clash, its location (level, grid and room), the systems involved, the person responsible, the agreed action and a due date. Track the total number of open clashes over time. A falling curve shows the coordination is working, while a flat one points to a problem in the process.

Avoid exporting thousands of individual clashes in a spreadsheet nobody reads. If the report cannot be reviewed in a meeting, it will not be acted on.

Common mistakes

  • Running clash detection once, late, as a box-ticking exercise just before construction.
  • Testing models that use different coordinates or are out of date.
  • Ignoring clearance and access zones.
  • Not modelling insulation, supports or builder’s work openings.
  • Treating the clash count as the goal rather than a buildable, maintainable ceiling void.
  • Leaving the specialist contractor’s fabrication models out of the final rounds.

What it means for cost and programme

Clash detection does not remove the need for coordination drawings or site supervision. What it does is move problems to the stage where they are cheapest to fix. On London projects, where ceiling voids are tight and existing structure is often irregular, that saving is significant. Fewer site queries, less rework, prefabrication you can rely on and a cleaner handover all follow from a model that has been properly coordinated.

It also improves the information you hand over. A coordinated model that reflects what was built is a far better starting point for maintenance and future fit-outs than a set of marked-up drawings.

Clash detection and ISO 19650

On projects run to ISO 19650, clash detection fits into the information management process. The client’s information requirements and the BIM execution plan should say how often federation and clash testing happen, which tolerances apply, and how issues are recorded and closed. Setting this out at the start avoids arguments later about who was supposed to find what.

In summary

Effective clash detection is a process, not a button. You need well-built models on shared coordinates, a clear clash matrix and sensible tolerances, regular coordination meetings and short reports that assign real actions. Done properly, it turns the ceiling void from a site problem into a solved design.

We provide BIM MEP services for design teams and contractors, from Revit modelling to federated clash detection and coordinated drawings. If the design itself is not yet fixed, start with our MEP design services. For fit-outs where the ceiling void is especially tight, see our page on office fit-out in London.

Need a model that is coordinated before it reaches site? We run Revit modelling, Navisworks clash detection and coordination meetings for London projects. See our BIM coordination services.
Contact

Need help with the building services on your project?

Call us, or leave your phone number and an engineer will call you back. We will not ask you to fill in a long form, and we do not store your details.

  • London and the Home Counties
  • Design-only, BIM-only or full design and installation
  • Revit, IFC and Navisworks deliverables

Request a call back