“Cat A” and “Cat B” are used on almost every London office letting, but they are rarely defined precisely. For building services, the difference matters a great deal. Much of the money wasted on office fit-outs goes on a landlord installing a full Cat A services package, only for the tenant to strip half of it out and replace it a few months later.
This guide explains what each category usually means for MEP services and how to plan the two stages so that less work is done twice.
The definitions in brief
- Shell and core: the base building. Structure, envelope, lifts, risers, main plant and landlord’s incoming services, with tenant floors left as open shells.
- Cat A fit-out: a floor that is ready to let and usable, but not designed for any particular occupier. It typically includes a raised floor, a suspended ceiling, base HVAC, general lighting, basic fire detection and small power distribution to the floor.
- Cat B fit-out: the tenant’s fit-out, designed around how they will actually use the space. It adds partitions, meeting rooms, kitchens, comms rooms, furniture and branding, along with the services changes those need.
Industry guidance, such as the British Council for Offices fit-out guide, describes typical Cat A contents. Each landlord’s own specification and design guide is the document that actually decides what is included.
What Cat A usually includes for MEP
HVAC
The base system is installed in an open-plan layout, designed to the landlord’s occupancy density and load criteria. Common systems in London offices are four-pipe fan coils, VRF with ducted or cassette indoor units, and chilled beams. Fresh air comes from central air handling units with heat recovery, ducted to each floor. Controls are typically connected to the landlord’s BMS.
Electrical and lighting
Cat A provides distribution boards for the floor, containment and small power in the floor void, and general lighting at open-plan design levels with presence and daylight control. Emergency lighting is designed for the open floor.
Fire and life safety
Cat A covers fire detection and alarm to suit the open layout. Sprinklers, where fitted, are installed for an open ceiling, and smoke control is part of the base build.
Public health
The landlord provides toilets and showers in the core, plus capped drainage and water points so that tenants can add tea points or kitchens.
What Cat B changes
Cat B is where the open plan becomes a real office, and nearly every partition affects the services:
- HVAC zoning. Each meeting room, quiet room and focus space needs its own control and enough capacity for its occupancy. A twelve-person boardroom has a very different load from the open-plan desk area it replaced. Fan coils or VRF units are relocated, added or re-zoned, and fresh air supply and extract are rebalanced.
- Comms and server rooms. These need dedicated, often resilient, cooling that runs all year, independent of the base system.
- Kitchens and tea points. These bring water, drainage, extract and extra power. Their location is limited by where drainage and risers can reach.
- Lighting. Lighting is redesigned around the new layout, with feature lighting, scene control in meeting rooms and emergency lighting adjusted to suit the new escape routes.
- Power and data. Floor boxes move to suit desks, AV in meeting rooms needs power and containment, and access control and security are added.
- Fire detection and sprinklers. Detectors and sprinkler heads must be adjusted to suit the new rooms and ceiling layout. Partitions can change escape routes and compartmentation, so fire engineering needs checking.
Where the waste happens
The classic example is a landlord finishing a floor with a ceiling grid, cassette units and lighting. A tenant then signs, designs a layout with a dozen meeting rooms and an exposed-soffit area, and much of the new Cat A is removed and stored or skipped.
There are a few ways to avoid this:
- Cat A+ or “Cat B ready” approaches. Some landlords install the main plant and distribution but hold back the final ceilings, indoor units and lighting until a tenant is known.
- Early tenant engagement. If the tenant is signed before Cat A completes, change the Cat A scope rather than building and then removing it.
- Flexible base design. Choose systems and distribution that adapt easily to partitions. For example, provide spare capacity and connection points, use modular wiring for lighting, and zone the system sensibly.
- Reuse. Where the Cat A has to come out, reuse units and fittings elsewhere in the building where possible.
Questions to ask before you start
For tenants
- What exactly is in the landlord’s Cat A, and in what condition?
- What capacity is available for cooling, fresh air and electrical load, and what does the lease allow you to add?
- Where can extra plant go? On many London buildings, roof and riser space are controlled tightly by the landlord.
- What does the landlord’s design guide require for materials, controls and connections to the BMS?
- What will you have to reinstate at the end of the lease?
For landlords
- Is a full Cat A the right product for this floor, or would a Cat A+ or shell let suit the market better?
- Does the base design leave room for typical tenant changes?
- Are there clear technical guides and as-built information for tenant designers?
Programme and approvals
A London Cat B fit-out has its own approvals process. That usually means landlord’s consent for the works, often with technical review by the landlord’s consultant, plus building control and sometimes insurer input on fire systems. Agree these routes early. Changes to HVAC zoning and fire detection are the items reviewers check most closely.
Commissioning matters as much at Cat B as at Cat A. Rebalancing air and water systems after partitions go in, testing controls room by room, and updating the BMS and record information are what make the new layout comfortable.
The role of coordinated design
On a busy Cat B floor, the ceiling void still contains the Cat A services, plus new ductwork, AV containment and sprinkler changes. Coordinated drawings, and on larger floors a 3D model with clash detection, avoid installers discovering conflicts with ceilings already up. Choosing the right system at the start also helps. If you are deciding how to cool meeting rooms, our guide to VRF vs split system choices compares the options.
In summary
Cat A provides a usable, open-plan base. Cat B turns it into the tenant’s office, and changes most of the services on the way. The more closely the two stages are planned together, the less is built twice.