LOD 300 vs LOD 400: what MEP contractors actually need
LOD is one of those abbreviations that appears in appointments and then causes an argument six weeks later. This note explains the difference, in plain language, between a coordinated design model and a model an installer can fabricate from.

LOD is a level of detail, not a badge
LOD stands for level of development, or sometimes level of detail, depending on which guidance note you are reading. The numbers most often used on UK MEP projects are 300 and 400. They are not a legal standard we can point to on every job, and different clients mean slightly different things by them. That is why the appointment has to define the content, not just the number.
Used carefully, the terms are still useful. They describe how much you can rely on the model for: coordination and quantities at one end, fabrication and installation at the other.
What people usually mean by LOD 300
A coordinated design model.
At this level the systems are the right type and the right approximate size, in the place they will occupy. A duct has a size and a route. A pipe has a diameter and a fall. A tray has a width and a clearance. Plant has a footprint, a height and a zone for access and replacement.
You can use a model at this level to find clashes, to agree plant rooms and risers with the architect, and to produce coordinated drawings. You should not assume that every bracket, every flexible connection or every manufacturer's exact casing is already in it.
For many design-only appointments in London, this is the right target: it proves that the services fit, and it gives an installer a coordinated design to work from, without pretending to be a fabrication model.
- Routes, sizes and plant positions proved in 3D
- Access and maintenance zones shown
- Suitable for clash detection and coordinated drawings
- Not automatically a complete fabrication model
What people usually mean by LOD 400
A model closer to installation and fabrication.
At this level the model includes more product-level information: specific equipment, supports, detailed connections, and the small items that decide whether something can actually be fixed in a shallow London ceiling.
This is the model a contractor wants when they are prefabricating pipe or duct, or when the site team is expected to install directly from the model rather than from a set of 2D drawings that still need interpretation.
It takes more time, more manufacturer information, and more decisions. If you ask for 'LOD 400' without agreeing which products, which supports and which tolerances, you will not get what you think you have commissioned.
What a contractor actually needs on a London site
Most installation problems we see are not caused by the absence of a manufacturer's exact casing in the model. They are caused by a duct and a beam trying to occupy the same space, or by a plant room that cannot be maintained. That is a coordination problem, and it is solved at the LOD 300 end of the work — provided the model is honest about sizes and access.
Where prefabrication or a very tight ceiling is involved, more detail is worth it. The conversation to have, early, is: will the installer build from the model, and if so, which elements need fabrication-level information?
If we are also the installer, we will tell you what we need in the model to do the work well. If we are modelling for another contractor, we will ask them the same question rather than hiding behind a number.
Agree it in the appointment
Before work starts, agree the intended use of the model, the file formats (Revit, IFC, Navisworks), the clash rules, and what 'done' looks like at each issue. If you are unsure, our BIM coordination page describes the service, and we can talk it through on a call.

Related guides and services
If you are appointing a model rather than reading about one, start with BIM coordination or MEP design. If the question is about fee, see the note on what drives the cost of design in London.
Related pages
Services
Questions about this guide
Is LOD a formal UK standard?
It is a widely used way of talking about model content, but the number alone is not enough. The appointment should describe what the model will contain and how it will be used.
Do I always need LOD 400 for installation?
No. Many installations are built successfully from a well-coordinated design model plus drawings. Fabrication-level detail is needed when the installer will build from the model, or when the tolerance is very tight.
Which files do you issue?
Typically Revit, with IFC and Navisworks when the team needs them, plus drawings issued from the same model.
Want to agree what a model should contain?
Call us, or leave your phone number and we will call you back to talk through the building, the team and the level of detail you actually need.
- London and the Home Counties
- Design-only, BIM-only or full design and installation
- Revit, IFC and Navisworks deliverables